Timeline surprises are the most common source of frustration in first co-packing runs. Brands assume production happens faster than it does, don't account for film lead times, or discover that a 14-day scheduling lead time means something different from when their materials ship.

Here's the complete, honest timeline for a sachet filling run at Overgang — every step, every dependency.

The Full Timeline

StepWho Does ItTime Required
Initial inquiry and quoteYou + Overgang1–3 business days
Formula finalizationYouVariable — must be done before scheduling
Film supplier selection and die line artworkYou1–2 weeks for artwork
Film printing and shippingYour film supplier10–12 business days after artwork approval
Ingredient ordering and deliveryYouVaries by supplier — typically 1–3 weeks
MSA signing and documentationYou + Overgang1–3 business days
Materials arrive at OvergangYou ship, we receiveMust arrive before run date
COA verificationOvergang1–2 business days
Production scheduling lead timeOvergang~14 days from confirmed specs
BlendingOvergangRun day (same day as filling)
Production runOvergang1 day (up to 20,000 sachets)
Packout and pallet prepOvergangSame day or next day
Outbound shipping to your warehouseCarrier1–5 business days depending on location

The Most Common Bottleneck: Film Lead Time

The step that surprises brands most consistently is film printing lead time. Your roll stock film isn't a commodity item you order from a shelf — it's a custom-printed, custom-sized product manufactured specifically for your brand and your pouch dimensions.

The process:

  1. You contact a film supplier and request die lines (the template for your pouch dimensions)
  2. Your designer uses the die lines to create artwork
  3. You submit artwork for film supplier approval (they check bleed, safety zones, bar codes)
  4. Artwork gets approved
  5. Film goes into production — 10–12 business days from approved artwork
  6. Film ships to Overgang

If you start the film process on Day 1, your film is unlikely to arrive before Day 30–35. That's before you've scheduled a production run. Brands who call us expecting a run in two weeks — when they haven't ordered film yet — are going to be disappointed. The film is the critical path.

Planning Your Timeline Backwards

The most reliable way to plan a co-packing run is to start with your desired finished goods date and work backwards:

In other words: if you want finished goods in hand on a specific date, you need to start the film process roughly 6–8 weeks before that date. Most brands don't account for this and end up pushing their timeline by 4–6 weeks on their first run.

What Overgang's 14-Day Lead Time Means

Our 14-day scheduling lead time means: once your specs are confirmed and your materials are on-site, we can schedule your production run within approximately 14 calendar days. It doesn't mean 14 days from when you reach out, or 14 days from when you order ingredients.

The clock starts when:

The fastest path to a short lead time is having all of those things in order before you reach out. The most common cause of delayed scheduling is one missing document — a COA that hasn't arrived, an allergen declaration that hasn't been submitted, an MSA that hasn't been returned.

The fastest possible timeline

A brand that has an established MSA with Overgang, pre-blended product ready to ship, existing film on hand from a previous run, and all documentation in order can go from "ready to run" to "production day" in as few as 7–10 business days. This is the repeat-customer scenario. First-time runs take longer simply because the onboarding documentation needs to be completed.