Production runs get delayed when brands aren't fully prepared at run time. The most common causes: a missing COA, a spec sheet that hasn't been submitted, film that arrives the day before the run instead of a week before. This checklist exists so none of those happen to you.

Phase 1 — Before You Contact a Co-Packer

Have these ready before your first inquiry:

Phase 2 — After You've Chosen a Co-Packer

Documentation

Film and Packaging

Ingredients

Phase 3 — Week Before Your Run

Phase 4 — After Your Run

The #1 cause of run delays

Late film. Film has a 10–12 business day production lead time after artwork approval. Brands who start the film process the same week they want to schedule a run are going to be disappointed. Start the film process 6–8 weeks before your target finished goods date and you'll never have this problem.

Quick Reference Checklist

ItemWhenStatus
Formula finalizedBefore contacting co-packer[ ]
MSA signedBefore scheduling[ ]
Allergen declaration submittedBefore scheduling[ ]
Spec sheet submittedBefore scheduling[ ]
Lot number format specifiedBefore scheduling[ ]
Film supplier identified6–8 weeks before run[ ]
Die lines obtained6 weeks before run[ ]
Artwork approved5 weeks before run[ ]
Film ordered (110%)5 weeks before run[ ]
Ingredients ordered (110%)3–4 weeks before run[ ]
COAs requestedWith ingredient order[ ]
COAs sent to co-packer1+ week before run[ ]
Film confirmed on-site1 week before run[ ]
Ingredients confirmed on-site1 week before run[ ]
Run date confirmed1 week before run[ ]